AQuA-RAT train #39239 · Arithmetic · Decimals & percentages
P works 25% more efficiently than Q and Q works 50% more…
P works 25% more efficiently than Q and Q works 50% more efficiently than R. To complete a certain project, P alone takes 50 days less than Q alone. If, in this project P alone works for 60 days and then Q alone works for 130 days, in how many days can R alone complete the remaining work?
This problem repeats another one in the library (at most with different numbers), so it's left out of browsing.
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #39239
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.