AQuA-RAT train #73331 · Algebra · Algebra word problems
Machine P can print one lakh books in 8 hours
Machine P can print one lakh books in 8 hours. Machine Q can print the same number of books in 10 hours while machine R can print the same in 12 hours. All the machines started printing at 9 A.M. Machine P is stopped at 11 A.M. and the remaining two machines complete work. Approximately at what time will the printing of one lakh books be completed?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #73331
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.