A painting crew painted 80 houses
A painting crew painted 80 houses. They painted the first y houses at a rate of x houses per week. Then more painters arrived and everyone worked together to paint the remaining houses at a rate of 5.25x houses per week. How many weeks did it take to paint all 80 houses, in terms of x and y?