Lemma
MediumAlgebra word problems
AQuA-RAT train #80205 · Algebra · Algebra word problems

NHAI employs 100 men to build a highway of 2km in 50…

NHAI employs 100 men to build a highway of 2km in 50 days working 8 hours a day.if in 25 days they completed 1/3 part of work .than how many more emploies should NHAI hire to finish it in time working 10 hours a day

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #80205

Stuck? A gentle nudge

No hints for this one.

Something off?
Workspace
Your answer

Checked against the answer in AQuA-RAT.