AQuA-RAT train #86798 · Algebra · Algebra word problems
A contractor undertook to finish a job in 150 days and employed…
A contractor undertook to finish a job in 150 days and employed 200 men. After 50 days he found that only 1/4 of work was finished. How many extra days are needed if he employs 50 more men?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #86798
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.